Travelodge site in Portsmouth is coming along nicely!

Construction of the new Travelodge in Portsmouth is progressing well.

The cores have been completed up to 10th Floor and the steel frame has been erected around the tower up to 7th Floor.

The steelwork erection has been complicated up to this point due to site restrictions, but now we are away from the concrete core area, it should progress rapidly to the point of starting to deck out the lower floors within the next couple of weeks.

What a difference a month makes!

What a difference a month makes! Fantastic progress on our latest Travelodge project in Finsbury Park.

A challenging 8 storey concrete frame with a split-level lower ground and basement which required the installation of a combination of a Contiguous Piled wall and CFA piles close to the Piccadilly Line.

In the space of a month the entire lower ground and basement levels have been completed and the first section of the upper ground floor ready for concreting. Main contractor – Harvard Knight; Concrete frame contractor - Oliver Connell and Son Ltd; Architect – The Harris Partnership; Consultant Civil and Structural Engineer – WFBA.

 
Travelodge project in Finsbury Park

Travelodge project in Finsbury Park

 

New Travelodge Hotel for Portsmouth

 
New Travelodge Hotel for Portsmouth WFBA Director Nick Groves
 

WFBA have been celebrating news that the construction of the 11 storey, 152 room hotel with under croft car parking, will start in November 2017. Working to designs by Maidenhead Architects SKDdesign, WFBA Director Nick Groves says that once opened in the spring of 2019, it will be the 20th hotel project for which the company  has provided consultancy services.

 

“Since April 2016 we have been looking at design options and assisting with obtaining planning permission, going thorough design development and producing final information for tender and construction.  Our team has used 3D modelling techniques to collaborate with the design and construction team in line with the principles of BIM.  Our experience with Travelodge enables us to support the proven formula that works for the successful group, and its team of architects and construction management team,” said Nick Groves.  “We are pleased to provide a vital link in the further expansion of this successful hotel chain.”

 

Hampshire based Management Contractor DNA IC Limited have been coordinating the design and build process on behalf of CHG Property Developments Ltd and will be building the new addition to Portsmouth’s skyline.

 

Helping Travelodge Expand

Nick Groves at the Andover Travelodge

Nick Groves at the Andover Travelodge

Director Nick Groves says that the expanding hotel group Travelodge has given his Romsey based consulting civil and structural engineering company WFBA very little time to rest as they have gain the instruction to apply their expertise to the 9th hotel project within the last 18 months.  This takes the total to 20 Travelodge projects since 2004.

 

In the South and South West of England, hotels at Weston Super Mare and Andover are the most recently opened, Harrow is in the final phase of construction and sites at Burnham on Sea, Swindon and Portsmouth are in the final stages of planning. Other project locations await instruction. Whilst for each project the Travelodge model is fairly standard, the sites are all different and require careful consideration as to the viability of the development in respect of the ground conditions and drainage solutions. Budgets are keen so design solutions need to be keen also.

 

“The latest sites are all multi million pound new build projects that we are involved with from the initial concept design and planning stages through to delivery on site. Our experience with Travelodge enables us to support the proven formula that works for the successful group, and its team of architects and construction management team,” said Nick Groves.  “We are pleased to provide a vital link in the successful hotel chain.”